Ministerial authorization application (EQA): steps, timelines and documents
Published on by Emphase Environnement

A ministerial authorization is required before carrying out a project that includes an activity with a moderate environmental risk, under section 22 of Quebec's Environment Quality Act (EQA). The application is filed online with the Quebec Environment Ministry, with forms specific to each activity and the studies that support them. The Ministry aims to make a decision within 75 working days of the application being deemed admissible. The quality of the file when it is filed therefore drives the schedule.
Certificate of authorization (CA) or ministerial authorization (MA)?
Both terms refer to the Ministry's permission required before carrying out an activity. People spoke of a "certificate of authorization", or a "CA application", before the EQA reform adopted in 2017. Since then, the official term is ministerial authorization, and the rules have been reorganized by the risk level of each activity.
Does your project need an authorization?
The system sorts activities into four risk levels, and the process changes at each level.
| Environmental risk | Process | Time to plan for |
|---|---|---|
| High | Environmental impact assessment and review procedure, then government authorization | The longest: impact study and public consultation |
| Moderate | Ministerial authorization (section 22 of the EQA) | Decision targeted within 75 working days of admissibility |
| Low | Declaration of compliance | To be filed at least 30 days before starting |
| Negligible | Exemption, if all conditions are met | No filing with the Ministry |
Section 22 of the EQA lists the activities that require an authorization, including:
- operating certain industrial establishments;
- water withdrawals;
- water management or treatment facilities;
- work in wetlands and bodies of water;
- hazardous materials management;
- equipment to treat emissions to the atmosphere;
- residual materials disposal or reclamation facilities.
It also covers, more broadly, any other activity likely to release contaminants into the environment or change its quality, including building an industrial establishment, using an industrial process and increasing the production of a good or service.
The Regulation respecting the regulatory scheme applying to activities on the basis of their environmental impact (REAFIE, page in French), in force since December 31, 2020, specifies for each activity whether it needs an authorization, qualifies for a declaration of compliance or is exempt. The same activity can change category depending on its size or how it is carried out. This is the first thing to establish, and a classification error is costly: starting without a required authorization is an offence.
The steps of a ministerial authorization application
1. Define the project and classify its activities
List every activity in the project, including those that are exempt or eligible for a declaration of compliance: the application must mention them. The Ministry recommends grouping a project's moderate-risk activities into a single application.
2. Ask for a pre-filing meeting if the project is complex
The Ministry offers a meeting before filing. It is used to discuss the project's issues, clarify the requirements that apply and confirm the expected forms and documents. It is useful when the project is well defined and your questions are specific.
3. Fill in the forms
The application is not a single form. It combines several, in this order:
- the activities and impacts identification form (AM16c), mandatory and filled in first: it produces the list of other forms to attach;
- the general forms, filled in directly in the online service: applicant identification, description of the application, declaration of prior record;
- one activity form for each activity concerned, for example hazardous materials management or atmospheric emission treatment equipment;
- the impact forms and supplementary description forms, depending on what is affected: surface water, groundwater and soil, among others.
The forms are updated with each regulatory change. Always use the current version, published on Québec.ca's page on preparing an authorization application (in French).
4. Gather the technical documents
This is the longest part. See the list in the next section.
5. File the application online
Filing is done in the Ministry's online service (in French). A professional can file it on your behalf, as your representative. A copy of the application must also be sent to the municipality where the project will be carried out.
6. Pass the admissibility review
The Ministry first checks that the file is complete. During this check, no new document can be filed.
- Complete file: you receive a payment notice.
- Incomplete file: you receive a notice of inadmissibility listing what is missing. You can refile, but the analysis has not started, and neither has the clock.
7. Pay the fees
You have 30 days after the payment notice, otherwise the application is closed and a new one must be filed. Fees vary by type of application and activity. They are indexed every January 1: the current schedule is published in the Ministry's fees page (in French).
8. Answer the analyst's questions
Once the fees are paid, the environmental analysis begins. The analyst may ask for additional information, documents or studies. You have 30 days to answer each letter. Only one extension can be granted per file, for up to six months.
9. Receive the decision
There are three possible outcomes: the project is authorized, authorized with additional conditions, or refused. Before imposing conditions or refusing, the Ministry sends a prior notice that lets you present your observations. A refused project cannot simply be refiled as is.
The documents to prepare
Section 23 of the EQA requires at a minimum a description of the activity and its location, and the nature, quantity, concentration and location of all contaminants likely to be released. The REAFIE (sections 16 to 18) details the rest. In practice, a file includes:
- identification of the applicant and, where applicable, of their representative and the professionals who prepared the file;
- the project description: processes, buildings, equipment, storage areas, schedule, residual materials generated and how they are managed;
- a georeferenced site plan, with work areas, discharge points and measuring or sampling points;
- a description of the environment, including any wetlands and bodies of water;
- expected impacts, mitigation measures and the monitoring and control program;
- technical studies prepared by qualified professionals, depending on the project: soil characterization report, hydrogeological study, ecological characterization, noise study;
- greenhouse gas emissions information, for the activities concerned;
- the declaration of prior record and a statement that the information provided is complete and accurate.
Two points relate directly to land. If the project involves a change in the use of land where a listed industrial or commercial activity took place, the authorization cannot be issued before the Ministry has received the land's characterization study (section 31.54.1). And in some cases, the REAFIE requires a groundwater monitoring program.
Real-world timelines
In its public service statement, the Ministry commits to a decision within a maximum of 75 working days of the application being deemed admissible. Its target is to meet that for 85% of applications. Three clarifications are in order.
75 working days is about three and a half months, and the clock only starts at admissibility. The time you take to answer requests for information is added on top. The Ministry itself calls processing time a responsibility shared between the applicant and the Ministry.
Complex projects take longer. The target does not apply to every file.
The study calendar can add a season. Some reports require surveys or samples that can only be done between May and November. If they are missing at filing, you have to wait for the next season: the Ministry warns this can delay the authorization by up to a year.
In other words, the real timeline starts the day you begin preparing the file. If your project has a start-up date, work backwards: field studies, file preparation, filing, then analysis.
Mistakes that delay an application
- Filing an incomplete file and planning to complete it later. It is deemed inadmissible and everything starts over.
- Using an outdated version of a form.
- Forgetting an activity. A treatment unit, hazardous materials storage or process water discharge may each require their own form.
- Underestimating field studies and missing the survey season.
- Giving inconsistent figures from one form to another: flows, quantities, concentrations. Each inconsistency becomes a question from the analyst.
- Missing a 30-day deadline, for payment or for a reply.
After the authorization
The authorization covers only the activities it describes, on the conditions it sets.
- Amendment (section 30). Before a change that results in a new release of contaminants or an increase in an authorized release, among other cases, the authorization must be amended.
- Transfer (section 31.0.2). If the business or activity changes hands, the authorization must be transferred, and a notice of transfer must first be sent to the Minister.
- Renewal. Some authorizations have a validity period. The renewal application must be filed before it expires.
- Follow-up. The authorization may require reports at the start, during or at the end of the work.
Having a professional prepare the file
You can prepare the application yourself. In practice, the studies have to be prepared by qualified professionals anyway, and the consistency of the whole file makes the difference between an application that is admissible the first time and several rounds of back-and-forth.